TM 11-5815-602-10
EE161-DM-OPl-010/E154UGC74
TO 31W4-2UGC74-1
Move the POWER switch to ON position.
q
. Based on the example given in paragraph 2-9d, the terminal will print out the
following Operation Validation/State Determination message for the RO state.
Example: Typical RO Operation Validation/State Determination Printout
SYSTEM INITIALIZED
SWITCH STATE - RO
OPERATIONAL STATE - RO
OPERATING CAPACITY - FULL
MODE - ASCII
BAUD RATE -1209
STOP BITS .2
END OF LINE OPTION - OD OD 0A
SPACE OPTION - OFF
LINE LENGTH -80
LINE FEEDS -1
RECEIVE ENVELOPE OPTION = 56 5A 43 5A 43: 4E 4E 4E 4E
TRANSMIT ENVELOPE OPTION = 56 5A 43 5A 43: 4E 4E 4E 4E 7F 7F 7F 7F
7F 7F 7F 7F 7F
PARITY OPTION = ODD
CAPITAL LETTER OPTION = ON
If a self-test is to be performed, it should be initiated after the State
Determination/Validation State message has been printed out and before
message date is stored in memory.
After completing operations, be sure all printing has stopped, then place the POWER
q
switch in the
position.
2-53